Shigezhuang 110KV Transformer Substation Is Built in 
          
          
          BIIIB The Main Body of the Project Completed, 
          
          It Will Be Put into Operation in November
        
          
        As many enterprises enter BIIIB 
          and other follow-ups are built and put into production in succession, 
          the electrical load of the base rises rapidly, thus, a new power supply 
          needs to be built to meet the load demand. Since this May, Shigezhuang 
          110KV Transformer Substation has been put into construction.
          
          Situated on the northern side of the Middle Road and the western side 
          of Street No. 2, Shigezhuang 110KV Transformer Substation covers 4050m2, 
          and the construction area is 2430m2. On the ground are two floors, and 
          underground is a three-meter-high cable interlayer. After its completion, 
          the transformer substation can not only settle the power supply issue 
          in BIIIB, but also can supply power to the surrounding regions.
          
          At present, the main body of the project has been completed, and others 
          such as the external and internal decoration and the construction of 
          the cable tunnel as well as the installment of power supply equipments 
          are being undertaken. It is estimated to be put into operation in the 
          end of this November.